9.1.2. Investment prospects
|
One of the key factors determining the future development of the
power industry and the Company's investment policy is the introduction of new advanced
technologies and equipment, and the increase of the attractiveness of investment projects |
To maintain a required engineering, scientific and technical potential
the Company applied new mechanisms for attracting investments; managers were getting more
responsible for the results of their investment decisions and for the efficient use of
investment resources, the existing investment risks management mechanism was being
adjusted.
RAO "UES of Russia" developed a programme oriented towards the application of
advanced technical solutions, accumulation of internal and external investment resources
(The Programme "5000 MW"). Preliminary feasibility studies were made for
projects of construction of new facilities and reconstruction of existing ones with a
capacity of not less than 5 thousand MW.
Foreign consultants were engaged to work on these projects. JSC
"PricewaterhouseCoopers Audit" conducted a financial analysis of the power plant
construction and re-equipment and the calculations of the financial efficiency of
investments in the construction of power facilities contemplated by the programme.
The Programme "5000 MW" was presented to Russian and foreign investors.
A standing Commission on investments into generating facilities headed by deputy chairman
of the Board Sergey K. Dubinin was created to supervise the implementation of the
Programme "5000 MW". Its aim is to co-ordinate the preparation and
implementation of the projects, to attract foreign investments, to consider and prepare
decisions on technical and financial issues related to the project, to determine the legal
and commercial structure of transactions, and make the necessary changes to the ownership
structure.
Programme "5 000 MW"
Object of investments |
Target of investments |
Capacity |
North-West CHP |
completion of 2nd unit CCGT-450 |
450 MW |
Pskov CPP |
completion of 3rd unit |
215 MW |
Nizhnevartovsk CPP |
completion of 2nd unit |
800 MW |
Kaliningrad CHP-2 |
construction of 2 units CCGT-450 |
900 MW |
Berezovskaya CPP-1 |
completion of 3rd unit |
800 MW |
Surgut CPP-1 |
construction of a unit CCGT-325 |
325 MW |
Tyumen CHP-1 |
construction CCGT-220 |
220 MW |
Dzerzhinskaya CHP |
completion GTPP-150 |
150 MW |
Upper Volga HPP Cascade |
technical reequipment |
190 MW |
Shekino CPP |
construction of 2 units CCGT-450 |
900 MW |
Ivanovskaya CPP |
construction of 2 units CCGT-325 |
650 MW |
Krasnodar CHP |
construction of a unit CCGT-450 |
450 MW |
|